East Side Access under Grand Central Terminal: —Brings the Long Island Rail Road to Manhattan's East Side, with 160,000 passengers a day arriving at the new, eight-track Grand Central hub 16 stories below Grand Central Terminal.
—To be completed by 2019. —Estimated cost is $8.3 million. No. 7 extension to Manhattan's West Side: —Links Times Square to the far West Side to attract development to Manhattan's "last frontier" of available land and the Hudson Yards development.
—To open in 2014. —Estimated cost is $2.1 billion. Second Avenue Subway on Manhattan's East Side: —Eases massive congestion on Lexington Avenue subway lines and opens far East Side to commuters. —First section to open in 2016.
—Estimated cost for first phase is $4.5 billion.